Week 75

The landscaping and L-Stein is making good progress, the external stairs are half-completed, the water connection from Stadt Kelkheim is made and the connection from electricity/water into the house is done. Telekom were there making their connection as well.
 
Plastering is almost completed (and makes the house very humid).
 
Change request (!) from the missus to add a shelf built into a wall in the shower - so more costs. Gate/steps to the Fussweg was not part of the contract - so even more costs.
 
But overall it is progressing nicely. Next week should see the underfloor heating put in - move in date by end-Feb looks likely unless we hit delays
 