Thursday, 29 December 2011
Thursday, 22 December 2011
Week 28
Same story, no progress.
Roof tiles are still packed up and in the garden; no idea why.
Rainwater tank still not fitted.
The extra window openings in the kitchen were done but in slightly the wrong place. The extension of a window opening was not done, no explanation why.
The only change I saw was some minor cuttings for the electric cables.
A positive is that the windows will be ordered from Schüco tomorrow with a 4 week delivery time.
Another contractor came to see the house with a view to potentially taking over - but said it was too risky for him and highlighted some mistakes that would have to be fixed first.
The architect wants more money as he now has to keep working on the project longer than expected.
The kitchen maker wants more money as the delivery will now be done in 2012 and so no longer with 2011 prices.
A reminder letter from BG Bau came threatening thousands in charges ... the contractor was supposed to have filled it out and returned it already - obviously not.
Anyone know a good lawyer?
Roof tiles are still packed up and in the garden; no idea why.
Rainwater tank still not fitted.
The extra window openings in the kitchen were done but in slightly the wrong place. The extension of a window opening was not done, no explanation why.
The only change I saw was some minor cuttings for the electric cables.
A positive is that the windows will be ordered from Schüco tomorrow with a 4 week delivery time.
Another contractor came to see the house with a view to potentially taking over - but said it was too risky for him and highlighted some mistakes that would have to be fixed first.
The architect wants more money as he now has to keep working on the project longer than expected.
The kitchen maker wants more money as the delivery will now be done in 2012 and so no longer with 2011 prices.
A reminder letter from BG Bau came threatening thousands in charges ... the contractor was supposed to have filled it out and returned it already - obviously not.
Anyone know a good lawyer?
Thursday, 15 December 2011
Week 27
Another week and ... well, apparently the roof tiles have arrived on site (though not fitted at all).
Friday, 9 December 2011
Week 26 - 6 months later
Another 7 days elapsed, and 1 day of physical work done. Roof is sealed, and a hole is dug for the Regenwasserzisterne. But there is no sign of a zisterne or any roof tiles.
Good news is that we have a new window-maker who seems a lot better and can do what the other cowboy said was impossible.
Good news is that we have a new window-maker who seems a lot better and can do what the other cowboy said was impossible.
Thursday, 1 December 2011
Thursday, 24 November 2011
Week 24

Telecom cable has been entered into the tube, can't see much else done.
However the Architect has had a big argument with the Fensterbauer - neither able to admit that they had done anything wrong, and both too proud such that the only resolution would have been one of them admitting to making a mistake (not likely).
The end result is that the Fensterbauer threw his toys out the pram and decided that he didn't need the business.
Great huh?
The Architect asked me how I would have handled being accused of making mistakes ... I said "we agree to disagree and focus on the next steps rather than the past", a concept that seems to be alien to some people.
Friday, 18 November 2011
Friday, 11 November 2011
Friday, 4 November 2011
Wednesday, 2 November 2011
Scope Change
Thursday, 27 October 2011
Sunday, 23 October 2011
Thursday, 20 October 2011
Thursday, 13 October 2011
Thursday, 6 October 2011
Week 17
Another small delay, scaffolding needed (why don't these people think of these things from experience?) - otherwise things ok.
Rohbau now finished next week.
We decided to add some extra windows in the kitchen, will cost an extra 1-2 grand.
We decided to make the living room larger and L-shaped and abandon the idea of having a small living room and a small office.
We decided to put the Luftwarmwasswerpumpe outside, will cost and extra grand - hopefully we can now re-use this room as the office/library/spare room/cinema room.
We decided to add some storage (a loft) above the play-room/hall/bathroom.
Luckily, still within budget (the guy may be slow, but he is comparatively cheap when I hear other people's stories!).
Friday, 30 September 2011
Monday, 26 September 2011
Thursday, 22 September 2011
Week 15 #2
The builders seem to be quite efficient - within 4 days we have the outside walls completed and work commenced on the ceiling.
They are struggling as the contractor has not provided building electricity or water to allow them to the cut the wooden ceiling ready for the concrete (whatever that means!). They have even asked if they could buy electricity from the neighbours!!!!
So nice to finally see progress from the mish-mash of Italian, Bulgarian and Turkish builders.
Monday, 19 September 2011
Thursday, 15 September 2011
Thursday, 8 September 2011
Week 13
Thursday, 1 September 2011
Thursday, 25 August 2011
Thursday, 18 August 2011
Week 10
Well, at least there has been progress in moving the neighbour's sewage pipe, but not finished and nothing else that was promised was done.
Time to get tough.
Time to get tough.
Thursday, 11 August 2011
Week 9 (Fortschritt?)
Another week, another on-site Jour Fixe, and still all I see is a hole in the ground.
But I am told that the neighbour's sewage pipe will be removed tomorrow and am told that next week I will see work on my foundations.
But I am told that the neighbour's sewage pipe will be removed tomorrow and am told that next week I will see work on my foundations.
Thursday, 4 August 2011
Week 8 (Loesung?)
So, the Eigentuemer recognises that it is his problem and his expense.
He will get an offer to move the pipe from my Construction company (other companies won't do it for insurance reasons as it concerns 2 properties). It is not possible to combine pipes so there is oe connection to the main city sewage pipe (unless the council turns a blind eye .... hmmm).
It ultimately needs to go in the Grundbuch, which takes up to 6 weeks!, but for now we have a mini contract which we can sign to allow construction to continue.
He will agree to take expenses, I will agree to let the pipe go through my land and allow him access in case of problems. Meanwhile, work on the land is still on hold.
He will get an offer to move the pipe from my Construction company (other companies won't do it for insurance reasons as it concerns 2 properties). It is not possible to combine pipes so there is oe connection to the main city sewage pipe (unless the council turns a blind eye .... hmmm).
It ultimately needs to go in the Grundbuch, which takes up to 6 weeks!, but for now we have a mini contract which we can sign to allow construction to continue.
He will agree to take expenses, I will agree to let the pipe go through my land and allow him access in case of problems. Meanwhile, work on the land is still on hold.
Thursday, 28 July 2011
Wednesday, 27 July 2011
It's NotAr Problem?
The Notar has confirmed that there is no Baulast and that the pipe has been laid illegally - so, how do I convince the new owner of the house behind to fork out to re-route pipes that he wasn't told would be problematic?
I'm gonna have to give him a call - I think my conversational German could really be put to the test here talking about legal stuff, planning permissions, sewage pipe connections etc.
:-(
I just hope he is not on summer vacation for x weeks because every delay means more rent in the current place.
I'm gonna have to give him a call - I think my conversational German could really be put to the test here talking about legal stuff, planning permissions, sewage pipe connections etc.
:-(
I just hope he is not on summer vacation for x weeks because every delay means more rent in the current place.
Tuesday, 26 July 2011
Week 7 (Literally, "oh s**t")
This little pipe is causing massive problems - this sewage pipe, running through my building site, from the house behind ... simply should not be there. Construction on my site will soon have to stop until the problem is resolved.
At a time of summer vacations for many stakeholders, this could cause delays.
Logically, how else is the house behind going to get its sewage to the main town connection sewage pipe behind my property (considering that my land used to be its garden).
However, somehow it was never registered with the city council (which happened a lot in the 60's, never enforced) - and my contract to purchase the land has no 'Baulast' giving them the right to have a pipe through my property.
The owner of the house thinks he bought the house legally and it is not his problem either (just wait til I block his sewage pipe!!!!).
The original owner/builder is probably no longer around.
Great, I am going to have a nasty disupte with my new neighbour before I have started construction.
Somehow I will have to redirect his pipe around my new house and through my garden (unless I am nasty and refuse), but he is going to have to pay for it!!!! I kinda feel sorry for the guy, he just spent ****loads on a new house only to find after the fact
a) his garden is actually not his garden after all, it is my land
b) he has a building site at his back door
c) his nice expensive view is going to be part-blocked by my house
and now
d) he is going to have to pay to re-route a sewage pipe which he never imagined would be a problem
not to mention
e) he will have to fork out some money to share the cost of fencing our properties off!
Someone, remind me why I had this crazy notion to build a house ... in a foreign country ... with more laws & rules than inhabitants!
Monday, 25 July 2011
First problem
Thursday, 21 July 2011
Monday, 18 July 2011
Japanese Knotweed
It seems that we have Japanese Knotweed on the site, I'm sure there wasn't any there before - but it is evil stuff and spreads from its rhizomes very easily.
Seems to be evil stuff but the Architect thinks it is nothing to worry about (maybe because he is Japanese?).
The Olympic sites have had to spend over 70 million quid eradicating Japanese Knotweed.
http://www.wiseknotweed.com/
http://www.channel4.com/
Could have come from the
Sunday, 17 July 2011
Week 5
Tuesday, 12 July 2011
Kitchen planned!
Nearly 6 months after we started (but still on track) we have finally agreed on layout, applicances, price, colours etc for our new kitchen.
About 22k, which has to be self financed, 25% up-front and the rest after installation. Not cheap, but it's considered a big kitchen and we didn't want to scrimp on such an important room!
About 22k, which has to be self financed, 25% up-front and the rest after installation. Not cheap, but it's considered a big kitchen and we didn't want to scrimp on such an important room!
Thursday, 7 July 2011
Week 4
Expecting to see this week
1. the site secured
2. the work on 'rohbau' commencing
3. the 'Bauschild' affixed on site
4. the 4 bordering neighbours informed of what will happen
Instead we see ... only a portaloo! and one neighbour informed (no answer from others, but personally I wouldn't open the door to these guys either!).
Apparently there has been some delay with the Vermesser (?) who marks out the land.
Not sure why, within 4 weeks, this couldn't have been sorted already.
Next week we are promised that the this will all be done and the 'Bagger' will be on site. Also it seems that the 8 week Rohbau planning had anyway a buffer built in so that, weather permitting, we are still on track.
Thursday, 9 June 2011
Verbal contract agreed
A good offer of EUR 310,000 to build the house and car-port. Shook hands with Mr Guel on a verbal contract and he agreed to:
a) start work immediately, taking the risk himself that he wouldn't get paid
b) provide an offer for extra items (e.g. rainwater tank, fence, electric gate, bi-fold door).
a) start work immediately, taking the risk himself that he wouldn't get paid
b) provide an offer for extra items (e.g. rainwater tank, fence, electric gate, bi-fold door).
Saturday, 29 January 2011
Subscribe to:
Posts (Atom)








