Thursday, 25 August 2011
Thursday, 18 August 2011
Week 10
Well, at least there has been progress in moving the neighbour's sewage pipe, but not finished and nothing else that was promised was done.
Time to get tough.
Time to get tough.
Thursday, 11 August 2011
Week 9 (Fortschritt?)
Another week, another on-site Jour Fixe, and still all I see is a hole in the ground.
But I am told that the neighbour's sewage pipe will be removed tomorrow and am told that next week I will see work on my foundations.
But I am told that the neighbour's sewage pipe will be removed tomorrow and am told that next week I will see work on my foundations.
Thursday, 4 August 2011
Week 8 (Loesung?)
So, the Eigentuemer recognises that it is his problem and his expense.
He will get an offer to move the pipe from my Construction company (other companies won't do it for insurance reasons as it concerns 2 properties). It is not possible to combine pipes so there is oe connection to the main city sewage pipe (unless the council turns a blind eye .... hmmm).
It ultimately needs to go in the Grundbuch, which takes up to 6 weeks!, but for now we have a mini contract which we can sign to allow construction to continue.
He will agree to take expenses, I will agree to let the pipe go through my land and allow him access in case of problems. Meanwhile, work on the land is still on hold.
He will get an offer to move the pipe from my Construction company (other companies won't do it for insurance reasons as it concerns 2 properties). It is not possible to combine pipes so there is oe connection to the main city sewage pipe (unless the council turns a blind eye .... hmmm).
It ultimately needs to go in the Grundbuch, which takes up to 6 weeks!, but for now we have a mini contract which we can sign to allow construction to continue.
He will agree to take expenses, I will agree to let the pipe go through my land and allow him access in case of problems. Meanwhile, work on the land is still on hold.