Friday, 25 January 2013

Week 84

Too cold, no progress.

My question is, why am I paying to have the heating on full if I am told that the minus temperatures outside mean there has been "no progress with the drying"?

Sunday, 20 January 2013

Week 83

Again the minus temperatures delay the house drying and delay the work.

The only progress was the blow door test for the KfW energy efficiency loan was done - all seems ok.

Also some plasterwork was apparently continued.

Thursday, 10 January 2013

Week 82

The house hasn't dried out enough yet - another 1-2 weeks are needed :-(
so the internal work is delayed.

Meantime the external work on the perimeter and steps to Fussweg is going on.

Also we chose a new Laminate for upstairs - Ahorn.

Saturday, 5 January 2013

Week 81

Again no work due to XMas break.