Thursday, 26 January 2012

Week 33

We have a roof going on!

Friday, 20 January 2012

Week 32

Very little again apart from some cabling.

Thursday, 12 January 2012

Week 31

Put a rocket up the GU's **** on Tuesday and (hopefully) it had had an effect.

Today there were the various sub-contractors on site for rohbau, electrics, roof, etc. Windows openings finally sealed too. Let's see next week.

Thursday, 5 January 2012

Week 30

Another week, again no progress - blaming the bad weather (wet and windy).
It is true, but we told him months ago to get the house finished before the bad weather came.

We also arranged a meeting on Tuesday at the Architect's office and the contractor turned up at the building site - kinda sums him up really.

The good news is that his other projects are coming to an end so hopefully he can now devote the right amount of time needed.