Wednesday, 10 July 2013
Bathroom problems
Towel rail in wrong place, horizontal toilet buttons put in vertically, mirrors not arrived (now no longer made), 1x soft close toilet seat doesn't close softly etc
Window mess
Didn't spot this before - complete botch job fitting the jalousie, and a cable elsewhere had now fallen down (we already had to have another jalousie fixed).
The aftermath
We found that there was no pipe from the kitchen sink ... it went into the ground!
A new pipe was laid and a hole needed to be drilled so the kitchen unit also had to be removed.
Friday, 3 May 2013
Week 98
Laminate completed, doors fitted, bathroom/WCs done. Plasterwork outside well underway. Removal company commissioned, satellite Internet installation booked, grass company offer requested ... the end is in sight!
Wednesday, 24 April 2013
Week 97
Insulation being completed, electrical works and satellite too ... laminate started - kitchen needs some corrections, inside ready in a week.
It also took 14 unanswered phone calls to my lawyer in 4 hours before he finally pulled his finger out and arranged a meeting with my old builder.
It also took 14 unanswered phone calls to my lawyer in 4 hours before he finally pulled his finger out and arranged a meeting with my old builder.
Wednesday, 17 April 2013
Week 96
Carport finished but looks mugly and it has a gap so that it can't be used without a ramp.
House has been painted inside.
Kitchen arrives Friday.
House has been painted inside.
Kitchen arrives Friday.
Monday, 15 April 2013
Saturday, 6 April 2013
Week 94
Remaining tiles being fitted .... and bath mounted. Car port nearing completion.
Seems we are hitting the home straight and the end is in sight.
Seems we are hitting the home straight and the end is in sight.
Friday, 29 March 2013
Saturday, 23 March 2013
Week 92
Humongous car-port almost finished and facade work started also this week - good progress made on that score.
Wednesday, 13 March 2013
Week 91
Today is the day, according to the contract, that we should be moving into the house. :-(
Bad luck struck us again this year with a long and cold winter. Just when we thought that Spring was hear with +15 C then this week has seen heavy snow and minus temperatures.
Hopefully from next week Spring really does come and then there are about 4-6 weeks of work left - end-April looks likely.
Thursday, 7 March 2013
Week 90
Tile works almost completed on ground floor and in bathroom plus good progress on the car port.
Despite the warm weather they only plan to start on the facade work on Monday ... which is when the minus temperatures return. Architect seems puzzled why I am asking that they can start 2-3 days earlier.
Despite the warm weather they only plan to start on the facade work on Monday ... which is when the minus temperatures return. Architect seems puzzled why I am asking that they can start 2-3 days earlier.
Friday, 1 March 2013
Week 89
Met the builder to iron out some details about flooring costs. Despite the cold he promised wrk would commence on the carport.
For money reasons we had to stick with initial contracted tiled stairs.
For money reasons we had to stick with initial contracted tiled stairs.
Sunday, 24 February 2013
Week 88
Despite the architect trying to rebuff my suggestion that f*** all has happened in 2 months, the builder now wants to delay the move in date by 3 months due to the cold winter.
I can't begin to say how p****d off I am.
Winter = cold. It doesn't take a rocket scientist to know that - so why didn't the builder plan to get the insulation done before winter??? Builders are definitely the people who flunked school.
Kitchen maker suggested passing by, architect told him (without me on cc.) not to bother as the house is too wet due to the cold winter and lack of insulation.
Architect stands to lose his cash cow once the house is finished of course.
Finally signed the contract this week.
I can't begin to say how p****d off I am.
Winter = cold. It doesn't take a rocket scientist to know that - so why didn't the builder plan to get the insulation done before winter??? Builders are definitely the people who flunked school.
Kitchen maker suggested passing by, architect told him (without me on cc.) not to bother as the house is too wet due to the cold winter and lack of insulation.
Architect stands to lose his cash cow once the house is finished of course.
Finally signed the contract this week.
Sunday, 17 February 2013
Week 87
As far as I can see, this week saw tiles being laid in the living room only and, as requested, a shelf cut into the shower wall.
Progress disappointing.
Progress disappointing.
Tuesday, 5 February 2013
Week 86
The tiles will arrive this week and they will be laid in the ground floor.
Meeting with lawyer took place but the builder didn't arrive as he was stuck in a Stau, sigh.
Week 85
Apart from some plastering work, no progress.
Despite the promises and the unusually warm weather, there was no work on the outside insulation - apparently the walls were still wet/cold.
A meeting with the lawyer to sign the contract as the lawyer canceled at short notice because he had no car, sigh.
Friday, 25 January 2013
Week 84
Too cold, no progress.
My question is, why am I paying to have the heating on full if I am told that the minus temperatures outside mean there has been "no progress with the drying"?
My question is, why am I paying to have the heating on full if I am told that the minus temperatures outside mean there has been "no progress with the drying"?
Sunday, 20 January 2013
Week 83
Again the minus temperatures delay the house drying and delay the work.
The only progress was the blow door test for the KfW energy efficiency loan was done - all seems ok.
Also some plasterwork was apparently continued.
The only progress was the blow door test for the KfW energy efficiency loan was done - all seems ok.
Also some plasterwork was apparently continued.
Thursday, 10 January 2013
Week 82
The house hasn't dried out enough yet - another 1-2 weeks are needed :-(
so the internal work is delayed.
Meantime the external work on the perimeter and steps to Fussweg is going on.
Also we chose a new Laminate for upstairs - Ahorn.
so the internal work is delayed.
Meantime the external work on the perimeter and steps to Fussweg is going on.
Also we chose a new Laminate for upstairs - Ahorn.
Saturday, 5 January 2013