Wednesday, 24 April 2013

Week 97

Insulation being completed, electrical works and satellite too ... laminate started - kitchen needs some corrections, inside ready in a week.

It also took 14 unanswered phone calls to my lawyer in 4 hours before he finally pulled his finger out and arranged a meeting with my old builder.



Wednesday, 17 April 2013

Week 96

Carport finished but looks mugly and it has a gap so that it can't be used without a ramp.

House has been painted inside.

Kitchen arrives Friday.






Monday, 15 April 2013

Week 95

Laminate arrived, doors to be fitted.

Saturday, 6 April 2013

Week 94

Remaining tiles being fitted .... and bath mounted. Car port nearing completion.

Seems we are hitting the home straight and the end is in sight.